Great progress made at Tessenderlo Kerley Geleen
Mid-January, the final permits for the Tessenderlo Kerley Geleen Thio-Sul® production facility were granted and since then, work on the new plant has been running at full speed. As was the case with the construction of our Thio-Sul® plant in Rouen, France, which was completed in 2017, all of the construction works are being supervised by one main contractor, Le Gaz Intégral.
While construction of the office building is already underway, the foundation works for the plant are also currently being laid. This process involves driving in total 227 piles into the ground, a process which will take few more weeks to complete.
The new plant in Geleen is expected to be fully operational by mid 2024. So stay tuned for further updates on the progress being made!